Michael is a founder of TargetProcess (agile project management software). His Mission is to provide solutions to real problems in agile projects. He wrote several books about web development and many articles related to almost all aspects of software development. Michael is a DZone MVB and is not an employee of DZone and has posted 48 posts at DZone. You can read more from them at their website. View Full User Profile

Cumulative Flow Chart in Kanban: Real Usage Example

02.16.2010
| 4373 views |
  • submit to reddit

Cumulative Flow diagram is a very good starting point for stop-the-line or retrospective meeting. Here is a real example from TargetProcess development.

You can see in the chart that we had a bottleneck in the beginning of December. It was caused by a quite complex user story. In theory a single user story should not affect cycle time significantly and should not create bottlenecks, but if you violate some rules it might be the case.

The user story was about replacing jQuery javascript framework with ExtJS framework. It took 1 month to implement by 1 developer. During this month we’ve made several releases and all went smooth. Then this user story was verified by testers and all existing acceptance tests were passed. So we’ve made a decision to merge this story to the main code line.

Unfortunately, after the merge quite many bugs were found in the build during smoke testing. These bugs took more than a week to fix, and during this time we were unable to release anything, since the merge was already done and the rollback was quite complex as well.

The lesson learned is to put more effort into testing of user stories that are more complex in nature. This particular story affected many places in the application and usual smoke testing was not enough. So we are going to introduce a new class of service (let’s call it  “technically complex story” so far :) which would mean more in-depth testing and verification before the merge.

In general, Cumulative Flow chart is a valuable tool to analyze historical data, but for emergency bottleneck identification Kanban Board is even better. If you have limits on Kanban Board, you see problems immediately.

 

Published at DZone with permission of Michael Dubakov, author and DZone MVB.

(Note: Opinions expressed in this article and its replies are the opinions of their respective authors and not those of DZone, Inc.)