What's the Ideal Sprint Length

12.28.2009
| 3698 views |
  • submit to reddit
Introduction

I may have blogged about this previously. I have written so many blogs, I can't recall any more. However questions regarding Sprint length surface on the forums regularly.

As per usual, the answers one must give always depends on the context and every context is different than the next. So let me start with the context - this is an excerpt of a post on the scrum development group on Yahoo. Incidentally, Yahoo groups is a good place to hang out. You learn a lot from all the questions and the different contexts facing teams around the world.

The Context

A team of 5 members currently working with 10-day sprints. They haven't managed in the previous 5 sprints to have 100% of the User Stories completed. It is typically around 60-70% completeness.

There is proposal to increase the sprint duration to 15 days "because doing review meetings and planning every 10 days is a lot of overhead" according to the team.

My thoughts

Let me start out by stating some facts ...

The official Scrum sprint length is 30 days. However I don't think (I don't have facts to back me up on this but it's the sense I get from all the communications on all the forums) there are many teams working to 30 days any more.

Much of the Agile community agrees that shorter Sprints are better. So 2 week Sprints and even 1 week Sprints are becoming more the norm.

Why are shorter Sprints better?

1. Well we have learned from the Lean folks that shorter Sprints means less work-in-progress which means shorter cycle times and overall less waste.

2. Additionally, shorter Sprints tends to stress your process, revealing any flaws. Like no automated build process, automated test harnesses our unit test frameworks. Fixing these flaws has a tendency to provide leaps in productivity gains for your organization.

So assuming you buy the argument that shorter Sprints are better. My initial quick answer to the question is don't try to lengthen the Sprint. Rather try to figure out why you're only hitting 60% - 70% of your originally committed goals.

By the way, 60% - 70% may not be that bad, after all you have a team that is currently demonstrating a consistent output Sprint after Sprint.

So that leads me to think that either the story point estimation is not consistent, or the team is just over-committing. So I would suggest that they do the following.

Try to really assess what is going on in the retrospective. Let team members speak freely about their thoughts on the matter.

I would definitely spend a little bit of time re-assessing the size of a few completed items i.e. if the story was 10 points originally, what would they estimate the size now, after the fact. Re-assessing the relative size may well fix the problem.

Some folks, most notably Ron Jefferies, would argue why do you need to get your estimation down pat. Well in my opinion for one, predictability goes a long way to help remove team stress. So its great for a team to say we can commit to say 100 points and deliver between 90 and 110 each Sprint. The business will love you for this.

Whats good about this problem in and of itself is that Scrum is doing what it's supposed to do; surface issues for the team to resolve. And if the team feels that going to 15 day Sprints is the right thing to do, so be it - it might well be. But I would try to first figure out why 2 weeks is not cutting it. Many teams make it work so it should be doable.

Hope this helps if you're in the same boat. If not at least if it provides food for thought!

Jack
agilebuddy

AttachmentSize
Clock.jpg8.11 KB
Published at DZone with permission of its author, Jack Milunsky.